0

I have a large (14x20) wood louver with a frame that is going over a return vent. Should this be installed first and then have drywall put around it, or should I install the drywall first, then cut out a hole for the louver?

1 Answer 1

1

Put up drywall first - it is easier to get it parallel to close walls since you could install drywall 1-2% off. If you are not attaching this to a run and it is an open return I would also suggest trying to get at least one side next to a stud. Often the support holes for these are close to the opening so even with a good anchor these get flimsy.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.