I'm looking at completely re-decorating the main bedroom in my house - some of it I'd like to do myself and some I'm planning to get tradesmen in to help speed things up. That said, I've never really got much into DIY before so I'm not entirely sure what to expect and which order to do things in.
The list of jobs (with relevant tradie in brackets) that I can think of are as follows, in the order I think makes the most sense:
In any order...
- Replace main light and swap light switch for dimmer (electrician)
- Replace two radiators (plumber)
- Replace fitted wardrobe track and sliding doors (joiner)
- Replace internal storage of fitted wardrobe (joiner)
- Replace window sill (joiner)
...then when they're all done...
- Paint walls (decorator)
...lastly...
- Replace carpet (carpet fitter)
- Replace curtain rail (decorator)
- Build new bed, drawers, bedside table (handyman)
I'm thinking that with replacing the radiators, fitted wardrobe etc there may be some plastering or something needed before painting, but since it's my first rodeo I figured it's best to get the opinions of people who've done this kind of thing before :)
Is this roughly the right order, or am I overlooking one or more potential headaches?