I realize that this question is similar to What is the order of tasks when refitting a bathroom? but since I have some different projects, I thought it would be appropriate to ask in a separate question.
I'm getting ready to remodel a bathroom and it'll involve a few sub-projects:
- installing subfloor
- installing tile
- installing bathroom fan/light/vent (for the first time - which will require roof vent)
- replacing drywall on walls (possibly on ceiling too)
- replacing vanity and sink fixtures
- replacing toilet
- replacing bathtub
- replacing lighting fixtures
- painting
My original plan was to demolish everything... then start on the subfloor... and then work on electrical while the walls are open. I don't know where things like painting fall in though... because I don't want to paint walls too early but it might be difficult to paint around fixtures once they're in.