0

I am trying to extend my back patio like this enter image description here

Eventually, I want to extend the full 18 feet, but for now I am planning to just do the 5 feet by 5.5 feet section in blue. This section will be attached to the existing patio and the house. My plan is this:

  1. Dig out the existing ground by 8 inches deep. This will provide for a 4 inch gravel subbase and a 4 inch patio.

  2. Pour the gravel subbase.

  3. Use stakes and 2x4s to make the frame.

  4. Put in the rebar grid.

  5. Glue asphalt-impregnated fiber board to the existing patio and house to create an isolation joint.

  6. Mix and pour cement.

  7. Screed concrete and smooth out top with 2x4s.

  8. Seal concrete.

My first question is this: Will I need to insert the rebar grid into the existing concrete and the house foundation? In other words, do I need a better connection between existing concrete and the new concrete or will the isolation joints be fine?

Also, is there anything that I am missing in this plan? Or is there anything that I should be aware of when taking on this project?

Thank you.

  • 1
    Effort wise you should just consider doing the whole 18 feet at once. You will also eliminate the extra joint at the 5 foot mark. – Michael Karas Jun 16 at 15:40
0

I would not not add rebar on that end and leave slab independent. I would get a mat and dig a little more dirt out build your 5 foot pour. Let mat run by three feet and is ready for the next section of pour and lock them together. And do each pour this way till done. slab will be some what as one pour. And finish each end as a exspansion joint.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.