Update:
After 2 hours of working on it. I was able to replace the old breaker with Schneider Din Rail 125A breaker that directly feeds the Siemens panel with 6 GFCI breakers. See: https://imagizer.imageshack.com/img923/1584/3pqfvs.jpg The remaining 1-pole breakers below the above (now subpanel to a 60A Siemens GFCI load side) would be slowly replaced with Din rail because they are individual 1-pole breakers that would only trip 1 phase with remaining 1 phase hot. But then what is the problem if I won't replace them anymore (it would take too much work and interruption of power which my elderly co-occupants won't like). Note in fuses, only one phase disconnects, so is there any serious problems if only one breaker trips (out of two 1-pole) if there is short circuit or overload?
original message:
I realized a huge mistake. In our main panel, 32 pieces of individual 1-pole breaker was used for 240v 2-pole phase to phase. See
We thought the external handle can trip the other partner. But it couldn't. The internal tripping mechanism can engage even if it's in On position, the external handle can't push the other to Off. So one leg is always hot. In 2-pole breaker, there is an internal common trip. Hence I will just remove the entire plug-in bus bar & breakers and replace them with Din Rail breakers that will feed off the 60A GFCI in the Siemens main breaker. Most new condominium & houses use din rail now in the country and I don't want to buy new set of 2-pole plug in breakers to replace the 32 pcs.
Now my question. Should I use din rail enclosure inside the original panel or just the din rail breakers (like this):
Or is it better to just remove the old panel case itself? But it looks hard, so I plan to just removed the bus bars and breakers leaving panel case intact.
After the plug in bus bar was removed. How can I put new screw over metal that is encased in concrete. Must we drill all the way to the concrete and put screw anchor in the concrete or is there a screw that can use the metal chassis itself without digging deeper into the concrete?