1

Our house is nearly complete and I am planning our next steps. We have plumbing rough-in pipes for a basement bathroom, and to save some money I am planning on doing the bathroom myself over the next few weeks/months. I have done a decent bit of googling and have yet to find a tutorial that shows how I can go from rough-in to bathroom.

Q: What are the steps I need to take in order to create a bathroom from the rough-in pipes, and is there an instructional resource I can follow along with?

Details:

  • The framing is already done since the rest of the basement is finished

  • The floor will be tile

  • The sink will be a pedestal

  • I am considering putting in a utility sink instead of a shower and making it so it can be swapped out for a shower if we sell. Anything I should know there?

closed as too broad by isherwood, ThreePhaseEel, Machavity, mmathis, Daniel Griscom Jan 9 '18 at 13:01

Please edit the question to limit it to a specific problem with enough detail to identify an adequate answer. Avoid asking multiple distinct questions at once. See the How to Ask page for help clarifying this question. If this question can be reworded to fit the rules in the help center, please edit the question.

  • Just bring out your supply and drain for the utility sink where they'll be hidden by a shower so you don't have finish drywall work to deal with. You can always cut open the drywall behind the shower surround to reconfigure later. – isherwood Jan 2 '18 at 21:10
  • is your drain pipe low enough that the shower won't need to be three feet off the floor (and thus 4 feet from the ceiling? – dandavis Jan 2 '18 at 22:02
  • Yeah, it's new construction, and all of the rough-in includes drainage already. – Forklift Jan 3 '18 at 15:42
4

Given what we know (virtually nothing), the question is too broad. Order of operations depends on a number of design and product choices. Here's a rough outline.

  1. Frame the walls. Be sure that your toilet flange is centered 12" from framing. Be sure that your other plumbing and cabinetry plans fit as expected.

  2. Run plumbing through the walls for your fixtures. Cap pipe stubs.

  3. Rough in electrical.

  4. Insulate and install vapor barrier as appropriate.

  5. Install tub or shower pan. Install shower surround if it goes against framing.

  6. Install drywall. Tape. Texture. Paint.

  7. Install flooring and cabinetry in the desired order. Depends on flooring which comes first. Ceramic tile tends to go in after cabinetry. Vinyl may go in before.

  8. Install trim woodwork (doors, casing, base, shoe).

  9. Install electrical devices and trim.

  10. Install shower surround if it goes over drywall.