1

This is going to be hard to explain, so please bear with me. I am shrinking down an old 8' sliding glass door Rough opening from what appears to have been an old garage door originally. The header seems sound, so I plan on framing in under it, about 24"x 80" between the foundation edge which was also the old rough opening edge, and the edge of a the rough opening I want. As this is for an exterior door I need a minimum clearance of 6" vertical before the bottom of new siding, to prevent water and other issues. I plan on building a mold to pre-cast a piece of concrete I have designed that will have embedded threads for the sill plate and holes for rebar to be epoxy fixed once in place and connected to existing structures.

My question is this, should I design this to sit on existing slab and set in place with hydraulic cement (my current plan) or should I cut out a chunk of slab and design this to fit down next to the slab?

Remember, this will not be load bearing as it is under the header for the old door. As such do I need to worry about 'punch through' with the new block as it will not be over a footer as far as I know.

Thanks for reading and thinking about this.

0

If you're not in an earthquake zone, I think you'll be fine. Otherwise, I would go with a more secure method of anchoring the new concrete to the old so that it won't scoot away in an earthquake, which could warp the glass and create an evacuation hazard.

0

Keil, if I understand your situation correctly it sounds like you're on the right path. I would set the precast on the existing concrete, but you'll want to seal all around with a silicone-based calk. I don't think you need to worry about any punch through, because it isn't load bearing. Good luck!

0

How we normally pour concrete whether it be on top of or next to an existing slab is to anchor it with rebar. Simply drill a hole every 3ft(min) using a bit 1/8in bigger than the rebar and either epoxy the whole and hammer the rebar into place or omit the epoxy if you wish.

Just make sure to keep at least 2in of clearance above the rebar to the top of the concrete.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.