0

Background: I live in Minneapolis. I am finishing my basement and in doing so will be adding a sub-panel. I am finishing up the details for the rough-in inspection (pre-panel install).

I was under the impression that everything should be ready for the receptacles, switches, and lights to be added. Meaning, for example, receptacles, and lights in series should be pigtailed but the actual outlets and lights shouldn't be connected.

I have multiple junction boxes as well to split a circuit to multiple lines. Given the above I would assume that I should make all connections. However, my father is adamant that they should be measured to length, cut off and labeled, but left disconnected.

Perhaps my google-fu is just terrible, but I can't find an answer either way.

Should all connections be made in a junction box for the rough-in inspection or should they be left to hang?

  • You're doing a lot of work to avoid a single phone call. Stop searching the internet, and call your local building department. – Tester101 Nov 2 '16 at 10:39
  • Touché. I'll do so today. – ErR Nov 2 '16 at 13:55
2

The answer ultimately lies with your AHJ (hint: call them), but where I am, everything has to be connected/pigtailed and ready for switches/outlets.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.