I have 24v / 8a (400w) of solar running into a Renogy Wanderer Li 30A 12V PWM. I noticed that when at peak input capacity there was a chance for the in line fuse (20a) to trigger. I've added another 200w of solar with a different charger (MPPT) to the system because the new panels are at slightly a higher voltage (37v) than the first set. Since then the the inline fuse in the first system will trip consistently when the batteries are in the top 80% of their charge.
My question is what causes this behavior? Is it a function of the PWM interval on the charger nearing 0ms in load length and acting as a short? I ask because I once thought to test my solar setup with a 400w bench power supply so there are subtleties here I may be missing.
The system inputs are 400w (2 x 24v) + 200w (1 x 37v) to a 12v battery bank. Both chargers support 12v.