Timeline for How to transition from underground schedule 40 PVC conduit to EMT inside building through concrete slab?
Current License: CC BY-SA 4.0
4 events
when toggle format | what | by | license | comment | |
---|---|---|---|---|---|
Sep 26, 2023 at 3:50 | vote | accept | cjc | ||
Sep 24, 2023 at 3:00 | comment | added | cjc | @Ecnerwal I really didn't want a junction because wall is already crowed with panel, control box, pipes. I only have two 90 degree sweeps (into and out of trench) and an offset to the panel box. It's the EMT to male threaded fitting I can't find. Is that set screws or compression on the EMT side? Does it have a name? | |
Sep 24, 2023 at 2:04 | comment | added | ThreePhaseEel | You can simplify that to a PVC female adapter with an EMT connector threaded into it | |
Sep 24, 2023 at 0:36 | history | answered | Ecnerwal | CC BY-SA 4.0 |