2 x 10-2 ininside EMT.: enter image description here 2 x 10-2 ininside Sched 80. PVC: enter image description here Any questions?

enter image description here

It doesn't look that awfulIt's actually worse than it looks in the drawing. But yeah, it'llIt'll be bind-up city. This is why oval cables are treated as a round wire of the large dimension.

2 x 10-2 in EMT.enter image description here 2 x 10-2 in Sched 80. enter image description here Any questions?

enter image description here

It doesn't look that awful in the drawing. But yeah, it'll be bind-up city. This is why oval cables are treated as a round wire of the large dimension.

2 x 10-2 inside EMT: enter image description here 2 x 10-2 inside Sched 80 PVC: enter image description here

It's actually worse than it looks in the drawing. It'll be bind-up city. This is why oval cables are treated as a round wire of the large dimension.

added 224 characters in body
Source Link
Harper - Reinstate Monica
  • 309.6k
  • 27
  • 294
  • 760

2 x 10-2 in EMT.enter image description here 2 x 10-2 in Sched 80. enter image description here Any questions?

enter image description here

enter image description here

2 x 10-2 in EMT.enter image description here 2 x 10-2 in Sched 80. enter image description here Any questions?

enter image description here

deleted 1 character in body
Source Link
Harper - Reinstate Monica
  • 309.6k
  • 27
  • 294
  • 760

(this works for all pipes except 3/4" schedule 80 PVC; for that, a #8 ground wire won't fit due to conduit fill limitations; the #10 ground limits you to 60A. But then, if it was schedule 80, I supremely doubt you got two #10 cables in there!)

That means you'll be able to support the load you have planned, plus a pretty good sized EVSE, wood shop, whatever will come up for you.

That means you'll be able to support the load you have planned, plus a pretty good sized EVSE, wood shop, whatever will come up for you.

(this works for all pipes except 3/4" schedule 80 PVC; for that, a #8 ground wire won't fit due to conduit fill limitations; the #10 ground limits you to 60A. But then, if it was schedule 80, I supremely doubt you got two #10 cables in there!)

That means you'll be able to support the load you have planned, plus a pretty good sized EVSE, wood shop, whatever will come up for you.

deleted 1 character in body
Source Link
Harper - Reinstate Monica
  • 309.6k
  • 27
  • 294
  • 760
Loading
added 208 characters in body
Source Link
Harper - Reinstate Monica
  • 309.6k
  • 27
  • 294
  • 760
Loading
Source Link
Harper - Reinstate Monica
  • 309.6k
  • 27
  • 294
  • 760
Loading