3

I just tore out a ton of particle board subfloor that was previously used for carpeting. The entire house has decking (2x6 planks) running on a 45 degree angle over joists with 3/8" plywood over the decking, with the exception of a few rooms where I tore out the particle board so just decking there. I'm trying to figure out how to attach more 3/8" plywood to the decking where I tore out the particle board. We are installing t n g hardwood eventually.

  1. Should I try to drive decking screws through plywood into the joists, or can I just glue and screw into the decking?

  2. Does the plywood need to be oriented perpendicular to the joists, even with the decking under already? Or should I orient the plywood so that it will run perpendicular to the hardwood we will install (so, parallel to the joists..)

  3. Should I take the time to level the plywood subfloor over the decking, or should I just wait until installing the actual hardwood tongue and groove to worry about leveling (or "flattening, as I suppose it will be)?

1 Answer 1

3

The 45 degree decking is the primary sub-floor. It's a technique that was widely used in the past, but has subsequently been replaced with simply dropping sheets of plywood down.

In answer to your questions:

1) You can glue and screw to the sub-floor.

2) In this case, it doesn't matter. The sub-floor is carrying the load diagonally. However, if there were no sub-floor, then you would want to go perpendicular. See this discussion on the subject.

3) Always - always - always level as you go. Fix the level at the soonest possible opportunity or it can be amplified by an order of magnitude.

0

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.