Take the 2-minute tour ×
Home Improvement Stack Exchange is a question and answer site for contractors and serious DIYers. It's 100% free, no registration required.

I am working on a house that the concrete piers on the back side have tilted, and pulled the ledger board and header away from floor joists. this resulted in the floor joists dropping over about a 30 foot span. so far we have fixed the water drainage issue causing the piers to tilt, we have raised the back side of the home and pulled the ledger and header back into position. the floor joists are now resting on the ledger board, but the joists lack around a half inch in certain spots from flushing up to the header.

the ledger is two 2x8 beams that have been nailed together, with the header being a 2x10 beam sitting on top of one of those ledger beams, like this (side view):

l         this is the header. this text is parallel to the floor joists.
ll        this is the ledger
lllll     this is the concrete pier

the people who built this home didn't use joist hangers; instead, they nailed ONE nail into the outside of the header going into the floor joists...

a couple of questions i need help with:

  1. the ledger boards have separated in three spots from one another, up to 3/4 of an inch, probably due to our jacking and pulling in activities. Could I use bolts, and bolt them back together? Or should I sister another 2x8 along their length, and bolt all three together? this would add another 1.5 inches for the joists to rest on, so that seems like a better solution, but not sure. also by doing this, I am thinking maybe the extra board would apply pressure to the concrete piers and allow them to pull back to level.

  2. Can I use joist hangers on the joists in the areas where it is still pulled away from the header board up to a half inch? There is not sag and the wood is all in good shape. Is there a problem with doing any of this?

I am not a carpenter by trade, my side is electrical, but I have framed out a few buildings in my time and I am very good with the tools needed.

share|improve this question
    
Can we get a picture? –  longneck Jan 17 at 15:32
    
A picture would help a lot. –  Bryce Jan 17 at 20:07
add comment

2 Answers 2

You need an engineer and an inspector to tell you what to do in this situation.

share|improve this answer
add comment

also by doing this, I am thinking maybe the extra board would apply pressure to the concrete piers and allow them to pull back to level.

Not. Going. To. Happen. You need to pour/build new piers from the footers up - they won't straighten up themselves, and were probably inadequate to begin with [they moved, Q.E.D.] Get the new piers set level and properly cured before setting the building back down. No fun, but that's how it is.

Adding the 2x8 makes sense for bearing. I'm not sure how far out a joist hanger can be, but I doubt half an inch is blessed.

share|improve this answer
add comment

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.