Take the 2-minute tour ×
Home Improvement Stack Exchange is a question and answer site for contractors and serious DIYers. It's 100% free, no registration required.

I have a raised square of concrete, about 42" by 42" by 6" in my basement. Its probably an "equipment pad" of some sort, not sure what it was originally for, but it is inconveniently placed. Its poured directly onto the slab.

I'm sure I can just go down with a sledge and whack it away, then smooth over with instant concrete but, I'm not experienced with basement slabs so what do I need to know?

Whats the quickest way to remove the thing and smooth things over with minimum fuss and mess?

share|improve this question
    
Any chance that the pad was a footing for a removed structural support? –  User58220 Oct 28 '13 at 18:36

3 Answers 3

If it was poured onto an already existing slab, I would try separating it from the slab first to see if it can be broken away and leave the floor intact. Note: The pad should weigh about 815 pounds (370 kg) so light duty efforts are inappropriate.

Obtain two heavy steel digging bars like this along with some scrap 2x4s or similar. With heavy gloves on, try to wedge the pointy end into the joint between the pad and floor by holding it mostly horizontal, but still a down angle of 30° so the point is against the floor and firmly swing it into position. Or use a hammer and cold chisel to chip out a notch right next to the floor so the flat end of the digging bar can get a grip underneath the pad.

If you can establish a catching point, place a 2x4 3–4 inches away from the edge and use it as a fulcrum to lift the pad. Recall leverage basics: If you push down on the far end of the bar with 100 pounds force and the fulcrum is one-tenth the distance from the other end, that is a 10:1 force gain, so you will be applying 1000 pounds of lift. If you can get it off the floor, insert the other bar with another (or a shared) fulcrum to raise it 1.5 inches off the floor. Slide in a 2x4 to support it at the lifted edge (this probably requires one or two helpers) and withdraw the bars.

Once the pad is mechanically separated, have some Wheaties and then swing a heavy sledge hammer (15+ pounds) approximately one-third the distance away from the supported edge. It is easiest to crack the pad by starting close to the edge. Don't be discouraged if you don't see any cracks even after a dozen husky whacks—especially with six inches. Each impact is being absorbed and is weakening the pad. However, while it is intact, it is strongest. Persist and it will soften, crumble, and eventually break. After the first crack, it will become much easier to break up.

Break it into convenient-to-carry pieces and dispose. Clean up underneath. Probably the floor will be in good condition if the pad was added much later than the floor. Otherwise, you might have to sand down bits that stick and smooth the floor.

share|improve this answer

No easy way. I would rent a jack hammer.

share|improve this answer
    
And some very good quality ear muffs. Send the rest of the family away to grandma's house for the day that you use the jack hammer. –  Michael Karas Oct 28 '13 at 1:14

Easier to pour more cement in basement and raise rest of floor to same level (sorry, that prolly was NOT funny) good luck, is no easy way but jack hammer then skim

share|improve this answer
    
6" of concrete may be a massive project if the basement is large, and if there are walls, you'd want to remove them and rebuild them after you're done. I think I'd go for the jackhammer myself. –  BMitch Oct 28 '13 at 11:25

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.