I have heard conflicting instructions regarding primer on drywall, some saying one and some saying two coats. The bucket of Killz2 itself says reapply after 1 hr, implying two coats are needed (I am sure they want to sell more product). I have also heard varying customer feedback regarding Killz2.

Is it enough to apply just one coat of Killz2 primer on drywall or should I go with two? I have already done some painting with just a single coat and it turned out fine.

share|improve this question
    
Lather, rinse, repeat! Does says how many times! Seriously though, I've used it quite a few times and once I applied two coats in a really bad bathroom. I think it's a judgement call. Paint is porous so uncovered (by Killz) mildew can still grow behind the paint or through it. –  Jason Jul 22 '13 at 18:09
    
what does it mean to lather? –  amphibient Jul 22 '13 at 18:23
    
It's a soap/shampoo joke, apparently a weak one. –  Jason Jul 22 '13 at 18:23
    
@amphibient in this case it's the act of applying soap suds. "lather, rinse and repeat" is a saying that means "do all the steps over again" –  wax eagle Jul 22 '13 at 18:24
    
does that mean do two coats? –  amphibient Jul 22 '13 at 18:57

3 Answers 3

up vote 1 down vote accepted

Yes one coat should be plenty for new drywall, you can get it tinted to be similar to your final paint color also to limit the number of paint coats you need after the primer potentially.

share|improve this answer

Well it isn't about how many coats it is about coverage. If all that you see is your white Killz then that is enough for all dry walls.

It is very hard to say 1 vs 2 coats. I paint heavy. One of my coats my be 1.5-2 of another person's. Your paint benefits from primer not the primer that is under the primer.

Now for wet applications (bathrooms mainly) I might put on 2 thick coats of something like killz to act as a greater barrier not to help the painting process.

Note - I have a paint crew that used to work for me. Their paint jobs looks perfect. They used two coats. But their first primer coat was thin (half mine) and there were definitely coverage issues. They were efficient vs my heavy style of just get it over with. They probably got their two coats on faster than my one but they did have to wait for drying time in between... and without the heavy hand theirs looked smoother.

share|improve this answer

I apply 2 coats when I'm covering a strong color, or when covering serious stains on the wall. The original Killz is oil based and I've heard that it covers better, but I've had no issues with a single coat over drywall using the water-based Killz2.

However, when I use Killz2 on raw wood, I use 2 coats. That is mostly because I sand in between coats to get a good clean finish.

Bottom line, if you can still see the color or patches of color after the first coat, either coat again, or spot coat.

share|improve this answer

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.