I would like to open up a wall made of cinder bricks between a finished basement (back split) and the garden shed that is an original part of the house.

I would then have the garden shed space framed in and insulated. I would put in a door between these two spaces and the garden shed would then be used a a closet for the apartment.

Do I need to have 6 foot steel heading installed?

share|improve this question
    
Well it depends if the wall you are removing is load bearing. I am thinking it probably is but we would need to know this before answering. –  DMoore Apr 21 '13 at 5:09

1 Answer 1

A block wall that is actually part of the original outside wall of the main structure is most certainly a load bearing wall or part of the foundation. It is possible to open a six foot section, but care must be taken to install a properly sized supported header or if block is still going to be above the opening, a steel lentil. You will need some temp supports while building this new opening. A bit more details of your proposed project and some pics would be helpful.

share|improve this answer

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.